ISO 19650-2:2018 pdf download

ISO 19650-2:2018 pdf download.Organization and digitization of information about buildings and civil engineering works, including building information modelling (BIM)
1 Scope
This document specifies requirements for information management, in the form of a management process, within the context of the delivery phase of assets and the exchanges of information within it,using building information modelling.
This document can be applied to all types of assets and by all types and sizes of organizations, regardless of the chosen procurement strategy.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content constitutes requirements of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
ISO 19650-1, Organization of information about construction works一Information management using building information modelling一Part 1:Concepts and Principles
ISO 12006-2, Building construction一Organization of information about construction works 一Part 2:Framework for classification
3.1.2.2 plan of work
document that details principal stages in the design, construction work and maintenance of a project and identifies the main tasks and people
Note 1 to entry: A plan of work may be extended to include the stages in demolition and recycling of a project.[SOURCE: ISO 6707-2:2017, 3.2.19, modified一Alternative terms“staging plan, US" and“project plan,US" have been removed; Note 1 to entry has been added.]
3.1.3 Terms related to information management
3.1.3.1 BIM execution plan
plan that explains how the information management aspects of the appointment will be carried out by the delivery team
Note 1 to entry: The pre-appointment BIM execution plan focuses on the delivery team's proposed approach to information management and their capability and capacity to manage information.
5.1.1 Appoint individuals to undertake the information management function
The appointing party shall have regard to the effective management of information throughout the project and reflect the long-term asset information management strategy, as described in ISO 19650-1 :2018, 5.3, by nominating individuals from within the appointing party's organization to undertake the information management function on behalf of the appointing party.
Alternatively, the appointing party can appoint a prospective lead appointed party or a third-party to undertake all or part of the information management function, in which case, the appointing party shall establish a scope of services.
In doing this, the appointing party shall consider:
-the tasks that the prospective lead appointed party or third party will be responsible for;
-the authority that the appointing party will delegate to the prospective lead appointed party or third party; and
-the competency (knowledge or skills) that the individuals undertaking the function will need.
NOTE Where the appointing party appoints a prospective lead appointed party or a third party to undertake all or part of the information management function, the use of the information management assignment matrix (Annex A) can help with establishing the scope of services needed.ISO 19650-2 pdf download.