ASME OMA CODE-2011 pdf download

ASME OMA CODE-2011 pdf download.Addenda to ASME OM-2009 Operation and Maintenance of Nuclear Power Plants.
ISTA-3000 GENERAL REQUIREMENTS ISTA-3100 Test and Examination Program ISTA-3110 Test and Examination Plans. Test plans shall be prepared for the preservice test period, initial inservice, and subsequent inservice test intervals. 1 Each inservice test plan shall include the following: (a) the edition and addenda of this Section that apply to the required tests and examinations (b) the classification of the components and the boundaries of system classification (c) identification of the components subject to tests and examination (d) the Code requirements for each component and the test or examination to be performed (e) the Code requirements for each component that are not being satisfied by the tests or examinations; and justification for substitute tests or examinations (f) Code Cases proposed for use and the extent of their application (g) test or examination frequency or a schedule for performance of tests and examinations, as applicable
ISTA-3120 Inservice Examination and Test Interval (a) Examination and test frequency shall be in accor- dance with the requirements of Section IST. (b) The examination and test interval shall be deter- mined by calendar years following placement ofthe unit into commercial service. (c) The examination and test intervals shall comply with the following, except as modified by subparas. ISTA-3120(d) and ISTA-3120(e): (1) InitialExamination andTest Interval: 10 yrfollow- ing initial start of unit commercial service (2) Successive Examination and Test Intervals: 10 yr following the previous test interval (d) Each of the inservice examination and test inter- vals may be extended or decreased by as much as 1 yr. Adjustments shall not cause successive intervals to be altered by more than 1 yr from the original pattern of intervals.
ISTA-3200 Administrative Requirements (a) ISTPlans shallbe filed withthe regulatoryauthori- ties having jurisdiction at the plant site. (b) The selection of components included in the test plan is subject to review by the regulatory authorities having jurisdiction at the plant site. (c) Application of the requirements of this Section shall be governed by group classification criteria of the regulatory authority having jurisdiction at the plant site. (d) The use of any Code Case is subject to acceptance by the regulatory authorities having jurisdiction at the plant site. (e) Revisions to a previously approved Code Case may be substituted for that Code Case with the accept- ance of the regulatory authorities having jurisdiction at the plant site.ASME OMA CODE pdf download.

下载信息
下载地址

匿名

发表评论

匿名网友